Please wait while we process your request

Tacoma Narrows Bridge Case Study Analysis

Words: 707 | Pages: 3

This essay sample was donated by a student to help the academic community. Papers provided by Pro-Papers writers usually outdo students' samples.
Download

Tacoma Narrows Bridge Case Study Analysis

 

The Design/Build Contract

 

            The design-built agreement between the Washington State Department of Transportation (WSDOT) and the Tacoma Narrows Constructors (TNC) was signed on July 16, 2002, and it resulted in the emergence of a contract award and procurement environment. A section of the agreement’s terms provided that besides designing and constructing the bridge, TNC was also required to upgrade the existing bridge and infrastructure for $849 million “firm fixed price” (FFP). It is important to note that this deal was a deviation from the conventional design-bid-build type of agreement, where a seller only implements the buyer’s project design plan. In this recent design-built contract between the WSDOT and the TNC, it was stated that the bridge part of the project was estimated to cost $615 million. It was further documented that the design of the bridge and other related services were to be offered by the TNC selected Parsons Corporation. The contract provided an initial schedule for the project, in which the parties agreed that the construction of the bridge would be completed in a record time of fifty-five months. Notably, the parties to this contract mutually agreed that the building of the bridge caissons was to commence seventeen weeks after the contract came into force. 

            The ‘open forum’ nature of the design discussions allowed the TNC to start the fabrication of the steel cutting edge for the key tower caissons within thirty days after the signing of the contract (Irwin, Stoyanoff, Xie, & Hunter, 2005; Viola & Spoth, 2007). A critical assessment of this contract reveals that it was attracting subcontractors and contractors from different parts of the world, including South Korea, the United States, and Japan. Another important element of the contract between the TNC and the WSDOT was that the TNC was required to provide for all the materials, tools, labor, machinery and construction equipment, transportation, utilities, heat, transportation, and other services and facilities crucial for the effective implementation and completion of the project. Additionally, this new type of construction agreement also stipulated that the TNC was entirely responsible for acquiring the relevant regulatory approvals, permits, and insurance coverage. In brief, the contract between the WSDOT and TNC can be described as a peculiar construction agreement, with features that depart from the traditional construction/building contracts. For instance, the TNC undertook the responsibility of settling the cost of all the inputs that were required for the successful completion of the project, and this feature of the contract was fundamentally beneficial to the buyer, in this case, WSDOT. Nonetheless, this contract specification was at the same time a continuous challenge for TNC. The agreement, for example, provided that TNC was to complete the project by April 2, 2007. In addition, the company agreed to upgrade the old bridge within eleven months. It is interesting to note that this contract stipulated that the liquidated damages for the project were to be tired, but this was dependent on the exceeded milestones, which, eventually, had cost implications on the part of TNC. Originally, it was estimated that the whole construction cost would be 760 million; however, on completion of the project, the total cost incurred stood at $722 million. Basically, this meant that the project’s savings was $38 million (Spoth, Whisler, & Moore, 2008).

Lessons Learned (Summary of Project Assessment and Analysis)

 

An in-depth analysis of the Third Tacoma Narrows Bridge reveals that the parties to this contract employed a novel project management strategy that enabled them to complete the construction of the bridge successfully. The contractual agreement between the WSDOT and TNC provided the much-needed flexibility in the procurement of the necessary resources. It is worth noting that under the contract, TNC was responsible for covering all the project’s costs and it became a critical advantage for WSDOT. The construction of the bridge was a huge success resulting in substantial cost savings. One lesson that can be learned from the case is that in a construction project, the buyer should consider negotiating for a contract that obliges the seller to take the responsibility for all the costs, including labor and materials. The significance of this approach is that in the long-term, the buyer is likely to make substantial savings of the project’s cost.

Work Cited

1

But I must explain to you how all this mistaken idea of denouncing pleasure and praising pain was born and I will give you a complete account of the system, and expound the actual teachings of the great explorer of the truth, the master-builder of human happiness.

2

"At vero eos et accusamus et iusto odio dignissimos ducimus qui blanditiis praesentium voluptatum deleniti atque corrupti quos dolores et quas molestias excepturi sint occaecati cupiditate non provident."

3

"On the other hand, we denounce with righteous indignation and dislike men who are so beguiled and demoralized by the charms of pleasure of the moment, so blinded by desire, that they cannot foresee the pain and trouble that are bound to ensue."

References

Irwin, P. A., Stoyanoff, S., Xie, J., & Hunter, M. (2005). Tacoma Narrows 50 years later—wind engineering investigations for parallel bridges. Bridge structures, 1(1), 3-17.

Spoth, T., Whisler, B, Moore, T. (2008). Crossing the narrows. Civil Engineering, 78(2), 38-47.

Viola, J. & Spoth, T. (2007). A new suspension bridge at the historic Tacoma Narrows site. Structure Magazine, 42-45.

Try it now!

USD
10

Calculate your price

Number of pages:

Order Now

Related samples

Delve into the transformative impact of Harriet Tubman's daring fugitive slave rescue missions. Uncover the stories of liberation, resilience, and… .

Harriet Tubman Essay Examples

0 / 5

135

Explore the transformative impact of vulnerability in forging deeper human connections by sharing and learning from failures, fostering empathy and… .

Failure Essay Examples

0 / 5

51

Uncover the challenges and compliance issues surrounding marijuana legalization and international drug treaties. This article explores the tensions… .

Marijuana Legalization Essay Examples

0 / 5

39

We can take care of your essay

24/7 Support

We really care about our clients and strive to provide the best customer experience for everyone.

Fair and Flexible Cost

Fair and flexible cost affordable for every student.

Plagiarism-free Papers

Plagiarized texts are unacceptable in the academic community, and our team knows it perfectly well. For this reason, we have strict plagiarism detection tools which we use for each of our orders.

Compliance with Any Deadline

The minimal timeframe needed to complete your paper is 6 hours. So if you need your paper by tomorrow, this is the job for our experts!